Dave Fletcher (see Problem 3.10) was able to determine
the activity times for constructing his laser scanning
machine. Fletcher would like to determine ES, EF, LS, LF, and
slack for each activity. The total project completion time and
the critical path should also be determined. Here are the activity
times:

ACTIVITY TIME (WEEKS) ACTIVITY TIME (WEEKS) (letter is activity and number is time)

 

 

A6       E 4
B 7       F 6
C 3      G 10
D 2       H 7

 

3.17

 

 

Bill Fennema, president of Fennema Hospitality, has

developed the tasks, durations, and predecessor relationships in

the following table for building new motels. Draw the AON network

and answer the questions that follow.

 

 

Activity   predecessor optimistic       Most       pessimistic

likely       OPTIMISTIC

MOST

LIKELY PESSIMISTIC

A        —      4       8        10

B       A        2       8         24

C       A        8      12       16

D       A        4       6         10

E       B         1      2         3

F       E,C      6       8        20

G     E, C     2      3         4

H       F          2      2         2

I        F          6      6         6

J      D,G,H    4     6        12

K      I,J         2      2        3

 

c) Based on the calculation of estimated times, what is the critical

path?

d) What is the estimated time of the critical path?

e) What is the activity variance along the critical path?

f) What is the probability of completion of the project before

week 36?

 

to be completed in excel on separate pages

Place your order
(550 words)

Approximate price: $22

Sign up below to post your homework.

By Creating an account, you agree to our Terms of Service and Privacy Policy.

The price is based on these factors:
Academic level
Number of pages
Urgency
Basic features
  • Free title page and bibliography
  • Unlimited revisions
  • Plagiarism-free guarantee
  • Money-back guarantee
  • 24/7 support
On-demand options
  • Writer’s samples
  • Part-by-part delivery
  • Overnight delivery
  • Copies of used sources
  • Expert Proofreading
Paper format
  • 275 words per page
  • 12 pt Arial/Times New Roman
  • Double line spacing
  • Any citation style (APA, MLA, Chicago/Turabian, Harvard)

Our guarantees

Delivering a high-quality product at a reasonable price is not enough anymore.
That’s why we have developed 5 beneficial guarantees that will make your experience with our service enjoyable, easy, and safe.

Affordable Prices

Gishomework provides technical homework writing service at the most affordable prices. Our transparent pricing system ensures that we produce a quotation based on the description of the ordered paper.

Read more

100% Originality

Any time you order a paper through Gishomework.com, you can be sure to receive original papers. Our GIS homework help writers ensure that the topic is well-researched to get as much information for the production of high-quality original papers.

Read more

Timely Delivery

At Gishomework, we never compromise on time. Our team of professional academic writers is always keen on the urgency of the paper for on-time delivery. We always abide by the timelines provided on the order form.

Read more

Professional Writers

Gishomework is a website that connects students from across the world with highly-qualified academic writers. We have hired writers from diverse educational backgrounds to ensure that students from different disciplines are catered for.

Read more

24/7 Availability

The best thing about our services is that our support system is always available to ensure that you get assistance at any time of the day. You can be sure to get instant responses whenever you reach out to us.

Read more

Unlimited Revisions

You have 7 days after the paper was completed to ask your writer for free revisions, in case you need any.

Read more